Project Name |
: Vung Ang Thermal Power Plant |
Location |
: Ha Tinh province, Vietnam |
Client |
: PMU of Vung Ang Power Petroleum – Quang Trach province |
Contract Value |
: USD30.292.000 |
Scope of Works |
: Switchyard 500KV and Supporting Items – Turnkey project |
Construction Period |
: 2012 - 2014 |
Description of the Project |
: |
The project is carried out by the consortium of contractors: Vietnam Industrial Construction Company (VINAINCON) - Bach Dang Construction Corporation (PSC) –Power Engineering Consulting Joint Stock Company No. 1 (PECC1) , in which VINAINCON is the leader of the partnership. Especially, this is the first 500kV distribution yard to be delivered in a turn-key method by a local contractor.
Breakthrough in the construction process of 500kV power distribution yard Vung Ang is the maximum localization rate so that the main package, first circuit, secondary circuit are all done by the Vietnamese manufactures. The main contractor supplies one 500kV / 220 / 35-150MVA single phase transformer with a combination of 35kV and an intermediate MBA developed by Dong Anh Electric Equipment Corporation. This is the second transformer 500kV Vietnam was successfully built after 500kV Nho Quan, Ninh Binh. Secondary packages include capacitor panel, telecommunication system by EVNTEC Energy Technology Joint Stock Company. All the equipment installation works implemented by the Power Construction No.4 Company Limited, member of VINAINCON . Only some of the equipment of the package was imported from the G7 countries provided by Alstom, GE.The project is carried out by the consortium of contractors: Vietnam Industrial Construction Company (VINAINCON) - Bach Dang Construction Corporation (PSC) –Power Engineering Consulting Joint Stock Company No. 1 (PECC1) , in which VINAINCON is the leader of the partnership. Especially, this is the first 500kV distribution yard to be delivered in a turn-key method by a local contractor.
Breakthrough in the construction process of 500kV power distribution yard Vung Ang is the maximum localization rate so that the main package, first circuit, secondary circuit are all done by the Vietnamese manufactures. The main contractor supplies one 500kV / 220 / 35-150MVA single phase transformer with a combination of 35kV and an intermediate MBA developed by Dong Anh Electric Equipment Corporation. This is the second transformer 500kV Vietnam was successfully built after 500kV Nho Quan, Ninh Binh. Secondary packages include capacitor panel, telecommunication system by EVNTEC Energy Technology Joint Stock Company. All the equipment installation works implemented by the Power Construction No.4 Company Limited, member of VINAINCON . Only some of the equipment of the package was imported from the G7 countries provided by Alstom, GE.